2021-10-04 00:00:00 Comment: Work not Started. 0%
|
2021-01-27 00:00:00 Comment: At the time of visit it was found that site was levelled and sub-base was prepared and the
work was at halt due to objection of local people.
For earth filling (depth more than 1.0’) L- section & 30%
|
2021-09-23 00:00:00 Comment: At the time of visit, WBM was laid in the streets at site.
At the starting point of the street and near the h/o Gurjit Singh, the thickness of WBM (2 layers) was checked and found in order i.e 150mm 80
|