1 |
2021-10-04 00:00:00 Comment: Work not Started 0%
|
2021-01-27 00:00:00 Comment: At the time of visit the work of dismantling of existing street was in progress.
The work of levelling of earth surface was in progress in street of Mittal
house.
Proper levelling of the surface m 30%
|
2021-03-10 00:00:00 Comment: The thickness of bedding sand and lean concrete was checked and found as 40
mm and 100 mm which is as per estimate.
Near electrical pole at the junction of street settled tiles must be rectified 80%
|
2022-07-01 00:00:00
Comment: •As per IS code minimum 8 samples (Paver blocks) test report were required but MC official has provided the test for 6 paver blocks which is not acceptable.
•The expenditure of this work is more 100% |