2021-02-07 00:00:00 Comment: Proposed site for const. of drain and DB paving. 0%
|
2021-02-24 00:00:00 Comment: For Earth filling having depth more than 1’ proper L-section & X-section showing the existing
natural ground level (NGL) & final proposed level of earth filling be prepared & provided to the
W 35%
|
2021-06-03 00:00:00 Comment: Near open fields DB flooring was found settled in area about 20’X8’.
Immediate rectification of the same must be ensured by the department.
As per CSR item no. 29.22, longitudinal and cross 80%
|
Comment: |