Inspection Details

Column Filters

Work Details

Name of WorkConst of DB Paving n/h/o Faqir Singh, Nachter Singh, Gurpinder Singh and buta singh w.no.15
Town NamePatran MC
District NamePATIALA
Approved Amount 8.64
Awarded Amount7.95
Award Letter Ref03/06 dt. 19.10.2020
Sr.No First Visit Progress Second Visit Progress Third Visit Progress Fourth Visit Progress
1 2021-02-07 00:00:00
Comment: Proposed site for const. of DB paving.
0%
2021-06-03 00:00:00
Comment: The joint of DB paving were not filled properly with tiba sand.  All joints for DB paving should be thoroughly filled with dry sand grouting which shall be applied to a thickness of not less than
45%
2021-08-27 00:00:00
Comment: Near h/o Nachatar Singh and Gurpinder Singh (at different places) the DB flooring was damaged in an area about 10’x4’, 8’x5’, 12’x3’and 4’x4’. For Earth filling having depth more than
80


Comment: