Inspection Details

Column Filters

Work Details

Name of WorkCC Flooring n/h/o Kulwant sectory ward No. 12
Town NamePatran MC
District NamePATIALA
Approved Amount 9.47
Awarded Amount8.71
Award Letter Ref03/04 dt. 19.10.2020
Sr.No First Visit Progress Second Visit Progress Third Visit Progress Fourth Visit Progress
1 2021-02-07 00:00:00
Comment: Proposed site for laying of CC flooring.
0%
2021-02-24 00:00:00
Comment:  The joint of DB paving is not filled properly.  No display board was found at site for showing description of work, estimate cost, specification, agency name & time period.  No record of
45%
2022-01-12 00:00:00
Comment: No test report of CC cubes and material used at site was shown/provided to TPA team. Near House of Sh. Gurpyar Singh, approx. 50% of the total work of CC flooring was found eroded which needs to be r
80