1 |
2021-02-07 00:00:00 Comment: Proposed site for const. of drain. 5%
|
2021-02-24 00:00:00 Comment: The joint of DB paving is not filled properly.
No display board was found at site for showing description of work, estimate cost,
specification, agency name & time period.
No record of 45%
|
2021-06-03 00:00:00 Comment: 31. The joints of DB paving were not filled properly with tiba sand in area about
150’X15’.
32. As per CSR item no. 29.22, longitudinal and cross slopes should be given for DB
paving.
33. Dry 80%
|
Comment: |