1 |
2021-02-07 00:00:00 Comment: Proposed site for const. of drain & DB paving. 5%
|
2021-06-03 00:00:00 Comment: As per NIT, the time limit for the completion of work was 3 months i.e up to date
18.01.2021, but the work is still in progress till date of inspection. No document
for the extension of time limit w 45%
|
2021-08-27 00:00:00 Comment: Near h/o Gurnam Singh (at different places) the DB flooring was damaged in an area about 20’x7’, 15’x6’, 10’x5’, 15’x5’ and 5’x5’. It should be rectified.
For Earth filling having 80
|
Comment: |