1 |
Comment:
|
2021-02-01 00:00:00 Comment: • At the time of visit the work was in progress.
• Depth of GSB laid was checked near Gurinder Singh house and found in order.
• SEC make ISI marked I/L tiles were being used a site.
40%
|
2021-03-23 00:00:00 Comment: Insufficient cement sand mortar found in brick masonry locking. 70%
|
2022-06-03 00:00:00
Comment: The length of street marked as A (366’8”) was checked randomly and found as as marked as per completion plan as well as record entry made in Measurement Book.
60mm thick Interlocking tiles SEC 100 |