1 |
2020-12-09 00:00:00 Comment: Proposed site for laying of I/L tiles. 0%
|
2021-01-06 00:00:00 Comment: At the time of visit preparation of sub-grade and Const. of Road Gullies
was in progress.
No display board was found at site for showing description of work,
estimate cost, specification, agenc 30%
|
2021-10-04 00:00:00 Comment: As per NIT, the time limit for the completion of work was 4 months i.e up to date 02.03.2021, but the work is still in progress till date of inspection. No document for the extension of time limit 70%
|
Comment: |