Column Filters

Work Details

Name of WorkLAYING INTERLOCKING TILE FROM GUJRA WALA QABRISTAN TO TUBEWELL NO-7
Town NameMalerkotla
District NameSANGRUR
Approved Amount 10.02
Awarded Amount
Award Letter Refnull
Sr.No First Visit Progress Second Visit Progress Third Visit Progress Fourth Visit Progress
1 2020-12-09 00:00:00
Comment: Proposed site for laying of I/L tiles.
0%
2021-01-06 00:00:00
Comment: At the time of visit preparation of sub-grade and Const. of Road Gullies was in progress.  No display board was found at site for showing description of work, estimate cost, specification, agenc
30%
2021-10-04 00:00:00
Comment:  As per NIT, the time limit for the completion of work was 4 months i.e up to date 02.03.2021, but the work is still in progress till date of inspection. No document for the extension of time limit
70%


Comment: