Inspection Details

Column Filters

Work Details

Name of WorkLAYING INTERLOCKING TILE ON ROAD LIC OFFICE TO SUNAMI GATE
Town NameMalerkotla
District NameSANGRUR
Approved Amount 12.2
Awarded Amount11.53
Award Letter Ref039/019 dt. 03.11.2020
Sr.No First Visit Progress Second Visit Progress Third Visit Progress Fourth Visit Progress
1 2020-12-09 00:00:00
Comment: Proposed site for laying of I/L tiles.
0%
2022-01-17 00:00:00
Comment: At the time of visit the work of laying I/L tiles was in progress at site. As per NIT, the time limit for the completion of work was 4 months i.e up to date 02.03.2021, but the work is still in progr
50
2022-02-17 00:00:00
Comment: At the time of visit no work was in progress at site. The thickness of bedding sand and lean concrete laid under 80mm I/L tiles could not be checked at site due to unavailability of labor and tools a
80


Comment: