2020-12-09 00:00:00 Comment: Proposed site for laying of I/L tiles. 0%
|
2021-01-06 00:00:00 Comment: At the time of visit preparation of sub-grade and Const. of RGs work was in
progress.
No display board was found at site for showing description of work, estimate
cost, specification, agency na 30%
|
2021-01-12 00:00:00 Comment: • The thickness of sand bedding + lean concrete + I/L tiles was checked near Gora hair saloon and Starting of road and found in order.
• No record of test reports of material consumed at site was 70%
|