Sr.No First Visit Progress Second Visit Progress Third Visit Progress Fourth Visit Progress
1 2021-01-07 00:00:00
Comment: Proposed site for P/L of I/L tiles.
0%
2021-03-19 00:00:00
Comment: Sample of bedding sand were collected in the presence of ULB officials along with Contractor. The sample sent to NABL accredited lab for its testing. The test report of bedding sand received from th
40%
2021-07-05 00:00:00
Comment:  As per NIT, the time limit for the completion of work was 2 months i.e up to date 28.02.2021, but the work is still in progress till date of inspection. No document for the extension of time lim
80%