1 |
2021-01-07 00:00:00 Comment: Proposed site for P/L of I/L tiles. 0%
|
2021-03-19 00:00:00 Comment: Sample of bedding sand were collected in the presence of ULB officials along with
Contractor. The sample sent to NABL accredited lab for its testing. The test report of
bedding sand received from th 40%
|
2021-07-05 00:00:00 Comment: As per NIT, the time limit for the completion of work was 2 months i.e up to
date 28.02.2021, but the work is still in progress till date of inspection. No
document for the extension of time lim 80%
|
Comment: |