1 |
2021-01-07 00:00:00 Comment: Proposed site for P/L of I/L tiles. 0%
|
2021-07-05 00:00:00 Comment: Near the shop of Thind Auto Electrical and Judge Machinery store, the
thickness of bedding sand and base concrete was randomly checked and
found in order.
No display board was found at site for 40%
|
2021-10-20 00:00:00 Comment: As per NIT, the time limit for the completion of work was 2 months i.e up to date 29.02.2021, but the work is still in progress till date of inspection. No document for the extension of time limit was 70
|
Comment: |