1 |
2021-01-29 00:00:00 Comment: Proposed site for laying of I/L tiles. 0%
|
2021-10-04 00:00:00 Comment: 1) At the time of visit end locking of I/L tiles with CC was in progress.
2) Near h/o Manjit Singh (at two points) & Dullet Niwas the thickness of bedding sand randomly checked & found in order i.e 45%
|
2021-10-04 00:00:00 Comment: 1) At some portions on the executed site, the CC end locking of I/L tiles wasfound damaged.
2) The portions of berms paved with I/L tiles were of varying width along the length of the road. Depart 80%
|
2022-01-24 00:00:00
Comment: • At the time of visit, the street was found paved with I/L Tiles.
• The length of berm marked as B= 682’9” in completion plan was checked & found same as per completion plan.
• Some items100% |