2021-01-28 00:00:00 Comment: Proposed site for laying of I/L tiles & Const. of boundary wall. 0%
|
2021-10-04 00:00:00 Comment: 1) At the time of visit the work was in progress.
2) Near Shamshanghat (at two points) the thickness of bedding sand randomly checked & found in order i.e 40mm and at same locations the thickness of 45%
|
2021-10-04 00:00:00 Comment: 1) The thickness of bedding sand was randomly checked In Shamshanghat (at 2points) and found in order i.e 40mm but at same places the average thicknessof lean concrete observed as 80mm instead of 100m 80%
|
2022-01-24 00:00:00
Comment: • At the time of visit, the footpath in shamshanghat was found paved with I/L Tiles.
• The area marked as B=62’-9” x 32’8” in the completion plan was checked and found same as marked in t100% |