1 |
2021-01-28 00:00:00 Comment: Proposed site for laying of I/L tiles & const. of drains. 0%
|
2021-10-04 00:00:00 Comment: 1) At the time of visit dressing of Earth work was in progress.
2) Fine sand was used under I/L tiles instead of coarse sand.
3) No display board was found at site for showing description of work, 45%
|
2021-10-04 00:00:00 Comment: 1) The thickness of bedding sand & lean concrete was randomly checked Near h/o of Sita Singh & Lal Singh and found in order i.e (Sand=40mm & lean concrete=100mm).
2) Near h/o of Sita Sing, Lal Singh 80%
|
2022-01-24 00:00:00
Comment: • At the time of visit the street was found paved with I/L Tiles.
• The length of the street marked as St. no 6=368’-6” & St. no 10=259’-6” in completion plan was checked at site and the 100% |