1 |
2021-01-28 00:00:00 Comment: Proposed site for Const. of Boundary wall. 0%
|
2021-10-04 00:00:00 Comment: 1) At the time of visit the plaster work on Boundary wall was in progress.
2) No display board was found at site for showing description of work, estimate cost, specification, agency name & time per 45%
|
2021-10-04 00:00:00 Comment: 1) The thickness of bedding sand was randomly checked in front of Gate of Kabristan (at 2 points) and found in order i.e 40mm but at same places the average thickness of lean concrete observed as 88mm 80%
|
2022-01-24 00:00:00
Comment: • At the time of visit, boundary wall was found constructed and I/L Tile flooring in front of main gate of Kabristan was found paved with I/L tiles.
• The length of wall marked as B in completion100% |