1 |
2021-01-28 00:00:00 Comment: Proposed site for Const. of park. 0%
|
2021-10-04 00:00:00 Comment: 1) At the time of visit sand filling in joints of I/L tiles work was in progress.
2) The thickness of bedding sand was checked in Shamshanghat (at two points) & found in order i.e 40mm and at same 45%
|
2021-10-04 00:00:00 Comment: 1) The joints of I/L tiles were not filled properly with sand. For proper interlocking of tiles, sand grouting should be done properly.
2) Approved design of boundary wall and grill was not provided 80%
|
2022-01-24 00:00:00
Comment: • The completion plan has improper measurement entries. It should be rectified.
• The length of the wall on which wrought iron grills were fixed was checked and found as per entry made in MB 51 P100% |