Inspection Details

Column Filters

Work Details

Name of WorkP/Laying 60mm interlocking tiles in from Silu to Yash Painter W.No-14
Town NameAhmedgarh
District NameSANGRUR
Approved Amount 13.02
Awarded Amount12.25
Award Letter Ref18/08 Dt. 05.11.2020
Sr.No First Visit Progress Second Visit Progress Third Visit Progress Fourth Visit Progress
1 2020-12-07 00:00:00
Comment: Proposed site for P/L of 60 MM I/L tiles.
0%
2021-10-04 00:00:00
Comment:  Sample of I/L tiles 8nos. 60mm were collected from site in the presence of ULB officials along with Contractor. The sample was sent to a NABL accredited lab for its testing. The test report for t
45%
2021-09-29 00:00:00
Comment: As per work order, the time limit for the completion of work was 4 months i.e up to date 04.03.2021, but the work is still in progress till date of inspection. No document for the extension of time li
80


Comment: