1 |
2021-09-30 00:00:00 Comment: Before starting of work Subbase should be compacted properly and Sufficient Photography
and videography before execution, during execution and after completion of work should be
done.
0%
|
2021-03-10 00:00:00 Comment: At random checked thickness of base concrete under I/L tiles flooring near mandir and found in order.
• Department must ensure the work is being executed as per the specification. Sub-standard work 30%
|
2021-05-19 00:00:00 Comment: 1) The thickness of bedding sand and base concrete under I/L 60mm tiles was checked near the H.No. 11 & H.No. 46 and found the bedding sand 10mm against 40mm and base concrete 90mm against 100mm. i.e. 70%
|
Comment: |