Name of WorkLaying interlocking Tiles at ward no.8 Street of Raju Tailor, Dev Samaj College adjoining street and Makhu gate Street
Town NameFerozepur
District NameFEROZEPUR
Approved Amount 24.05
Awarded Amount23.63
Award Letter Ref
Sr.No First Visit Progress Second Visit Progress Third Visit Progress Fourth Visit Progress
1
Comment:

2021-09-30 00:00:00
Comment: At random the thickness of bedding Sand laid under interlocking tiles was checked at two points found 20mm instead of 40mm. Engineer-in-charge should thoroughly inspect the site and check the at s
45%
2021-03-10 00:00:00
Comment: At random checked, the thickness of sand under I/L tiles flooring checked near Ramesh Bhalla house and Electric Pole no. T/1810 and found 05mm&10mm against the provision of 40mm. Department must ensur
70%