Inspection Details

Column Filters

Work Details

Name of WorkLaying interlocking Tiles at ward no.3 Bari Street, Chungi Khana Road
Town NameFerozepur
District NameFEROZEPUR
Approved Amount 24.15
Awarded Amount23.67
Award Letter Ref23/27 dt. 15.09.2020
Sr.No First Visit Progress Second Visit Progress Third Visit Progress Fourth Visit Progress
1
Comment:

2021-09-30 00:00:00
Comment: Near Shop of kuldeep, the thickness of lean concrete + bedding sand + I/L tiles found 150mm instead of 200mm. AME/JE should check the thickness at some more points & the payment of actual work exe
45%
2021-03-10 00:00:00
Comment: At random checked the thickness of sand/Base Conc under I/L tiles flooring near 16 Sethi Niwas and Asiya Beauty Parlour and found 15mm & 70mm against the provision of 40mm and 100mm. • Department
70%


Comment: