1 |
2021-02-05 00:00:00 Comment: Proposed site for P/F of I/L tiles. 0%
|
2021-02-05 00:00:00 Comment: Thickness of Lean concrete was laid near stadium was not checked due non Availability of labours. At some places lean concrete laid under interlocking tiles was found loose and not compacted properly. 45%
|
2021-03-12 00:00:00 Comment: 1) Near Saloon Shop, the thickness of bedding sand and base concrete under I/L 60mm thick tiles was checked and found as per contract specifications.
2)Undulations were observed at many portions whic 70%
|
2023-03-14 00:00:00
Comment: •The final date of completion has not been mentioned on the MW-12. Engineer in charge must ensure that the work is completed under the given time extension or necessary recovery/LD charges should be100% |