2021-02-05 00:00:00 Comment: Proposed site for Construction of park. 0%
|
2021-02-05 00:00:00 Comment: The work of levelling of park is in progress. 30%
|
2021-12-23 00:00:00 Comment: At site, construction work of boundary wall and fixation of grills on wall were completed at site.
The grills installed on wall found rusted at the time of visit, these should be painted as soon as p 80
|
2023-03-14 00:00:00
Comment: •At site dimension of grills installed on wall was checked and found 9’7’’X3’1”. i.e. in order.
•The earth work was done as site, but no level sheet was submitted by the department afte100% |