Name of WorkP/F Interlocking Tiles from Ajij Depoo to H/o Master Balbir Singh on both side road at Ward No. 8
Town NameMamdot
District NameFEROZEPUR
Approved Amount 7.63
Awarded Amount7.36
Award Letter Ref19/6 dt. 10.11.2020
Sr.No First Visit Progress Second Visit Progress Third Visit Progress Fourth Visit Progress
1 2021-02-04 00:00:00
Comment: Proposed site for P/F of I/L tiles.
0%
2021-02-05 00:00:00
Comment: At random the thickness of Lean concrete, sand and interlocking tiles checked laid near SBI ATM found 165 mm instead of 200 mm. Sand grouting was not done properly and depression of tiles was found n
45%
2021-03-12 00:00:00
Comment: 1) At the time of visit, work of Tile flooring on berms of road was in progress. 2) In front of SBI Bank and Duggal Khaad Store, the thickness of bedding sand and base lean concrete under I/L 60mm t
70%
2023-03-14 00:00:00

Comment: •At site the length of the left side berm was checked and found as per completion plan provided by the department. •In this visit the thickness of bedding sand and lean concrete under 60mm I/L ti100%