1 |
2021-02-01 00:00:00 Comment: Proposed site for laying of I/L tiles. 0%
|
2021-02-22 00:00:00 Comment: The thickness of sand and lean concrete under interlocking tile flooring checked near
house of Jyoti Madam and found as per estimate.
ï‚· At some location surplus sand was lying over the paved stree 45%
|
2021-11-29 00:00:00 Comment: At about 5 meters ahead from the starting point of the Street, the thickness of
bedding sand and base concrete was checked at 2 points and found in order i.e
40mm(Sand)+100mm (Base concrete).
ï‚ 80%
|
Comment: |