2021-02-01 00:00:00 Comment: Proposed site for Construction of Boundary wall & shed. 0%
|
2021-02-22 00:00:00 Comment: The grill laid on the boundary was not painted yet.
The plastering on inner side of boundary wall should be done as per specification.
The usable dismantled material be accounted as per depa 30%
|
2021-05-20 00:00:00 Comment: 1) Some waste construction material (Malba) was lying near the newly construction boundary wall, which needs to be cleared.
2) For construction of shed sheets and steel sections/trusses have been use 80%
|
Comment: |