1 |
2021-02-01 00:00:00 Comment: Proposed site for P/L of I/L tiles. 0%
|
2021-02-22 00:00:00 Comment: Near Rice Mills it was observed that fine sand was used instead of coarse sand.
Rectification of the same should be done by the department before making final
payment to the agency.
The thickne 45%
|
2021-05-20 00:00:00 Comment: 1) Fine sand was being used at site as bedding for laying I/L tiles instead of coarse sand.
2) The thickness of base concrete under I/L tiles flooring was checked approximately about 15 meters from s 70%
|
Comment: |