2020-11-07 00:00:00 Comment: • In the sanctioned estimate the provision of the removal of malba with volume of 37.72m3 and lead of 07Km has been made but, No approved lead plan shown /provided to TPA team.
• In the sanctione 5%
|
2020-12-09 00:00:00 Comment: Laying of kerbstone & lean concrete thickness found in order in gupta hospital street 40%
|
2022-10-27 00:00:00 Comment: • Near H/o Subhash Pathanwala and H/o Lalit Sharma, cover frame of R/G were found broken and R/G was not properly plastered from the inside. It needs to be rectified.
• Near H/o Rajkumar, conditi 85%
|