Name of WorkConstruction of street Main Balgan Road to H/o Balli Saab towards H/o Master Ramjit to h/o Pandit Dinesh Sharma to h/o Gurdev Singh Ward No 04
Town NameDasuya
District NameHOSHIARPUR
Approved Amount 12.71
Awarded Amount12.58
Award Letter Ref6/7 16/11/2020
Sr.No First Visit Progress Second Visit Progress Third Visit Progress Fourth Visit Progress
1
Comment:

2021-01-08 00:00:00
Comment: • During the time of visit, the work of dismantling of old street surface was in progress at site. • Compaction of the surface was also being carried out at site during the time of visit. • Th
30%

Comment: