1 |
2022-01-13 00:00:00 Comment: At the time of visit the work was just started.
The existing roads were katcha road.
Proper X-sections should be prepared before starting the filling of earthwork
(more than 01 feet) p 0%
|
2021-10-01 00:00:00 Comment: R/G chambers were also being built at the site during the time of visit.JE
should ensure RG construction as per CSR specification. 30%
|
2021-09-22 00:00:00 Comment: During the site visit, the work of laying of Interlocking tiles was in progress.
‘RK’ make ISI marked M-35 thick I/L tiles were arranged and laid by the agency but copy of ISI license issued to 70%
|
Comment: |