2022-01-13 00:00:00 Comment: At the time of visit the work was not started.
The existing roads were katcha road.
Proper X-sections should be prepared before starting the filling of earthwork
(more than 01 feet) p 30%
|
2021-01-28 00:00:00 Comment: Near ML Electronics & other area the thickness of GSB found 3”. SDE/JE should check the thickness at some points and ensure that payments of actual work be done.
Before laying of WBM the Sub-ba 40%
|
2021-04-10 00:00:00 Comment: At the time of visit no work was in progress.
The thickness of BM & SDBC was checked near ML electrical work and found in order.
The work of BM &SDBC found loose at the edges of the road, needs to 70
|