2022-01-13 00:00:00 Comment: The existing roads were katcha road.
Proper X-sections should be prepared before starting the filling of
earthwork (more than 01 feet) proper compaction should be done& the
record of compaction sh 0%
|
2021-01-28 00:00:00 Comment: Near Buti Enclave & and other area WBM found laid could not be checked due to unavailability of required labours & tools. SDE/JE should check the thickness at some points and ensure that payments of a 40%
|
2021-04-10 00:00:00 Comment: Honey combing/ Segregation of aggregate in laid SDBC was observed near double transformer at site
(approx. 15 sq. mt.).
Near Industries Manhole cover found not properly placed and also found broken. 70
|