Inspection Details

Column Filters

Work Details

Name of WorkConst.of various streets in w.no.45
Town NameMC Jalandhar
District NameJALANDHAR
Approved Amount 36.33
Awarded Amount27.28
Award Letter RefCE/W/100 09/11/2020
Sr.No First Visit Progress Second Visit Progress Third Visit Progress Fourth Visit Progress
1 2021-10-03 00:00:00
Comment: Work not started.
0%
2021-09-22 00:00:00
Comment: Thickness of CC was checked near h/no-92 and found 2.5” instead 4”. SDE/JE should check the thickness of CC at some more points and payment of actual executed work should be made to the contractor
70%
2021-04-10 00:00:00
Comment: At Near Baba Baliknath mandir RMC was found laid, but In the absence of labour & tools, thickness of laid RMC could not be checked. SDE/JE should check the thickness of RMC laid & the payment of act
70


Comment: