1 |
2021-10-03 00:00:00 Comment: Work not started. 0%
|
2021-09-22 00:00:00 Comment: • The work of Laying WBM was completed at site. It was observed that the gradation of stone aggregates was not proper. JE/SDO should check thickness & quality of WBM at different points before relea 50%
|
2021-10-04 00:00:00 Comment: The thickness of BM &SDBC checked near fashion point & found 60mm and 65mm instead of 70mm. SDE/JE should check the thickness at some more points & the payment of actual work executed at site should b 70
|
Comment: |