Name of Work | Prov.W/S in various abadies along Majitha road & Silver estate beyond M.C. limit(Amritsar(MC)) |
Agency Name | M/s. R.S. Builders |
Project Cost | Rs 156 Lacs |
Start Date | 16-05-2016 |
End Date | 15-09-2016 |
Expected Date Of Completion | 15-09-2016 |
Je Incharge | Sh. Deepak Kumar |
SDE Incharge | Sh. Harpreet Singh |
Engineer Incharge | Sh. S.K.Ranga |
Dates | |||||||
---|---|---|---|---|---|---|---|
2024-12-03 | No Visit | Work Detail | Net Progress | ||||
2024-12-02 | No Visit | Work Detail | Net Progress | ||||
2024-12-01 | No Visit | Work Detail | Net Progress | ||||
2024-11-30 | No Visit | Work Detail | Net Progress | ||||
2024-11-29 | No Visit | Work Detail | Net Progress | ||||
2024-11-28 | No Visit | Work Detail | Net Progress | ||||
2024-11-27 | No Visit | Work Detail | Net Progress | ||||
2024-11-26 | No Visit | Work Detail | Net Progress | ||||
2024-11-25 | No Visit | Work Detail | Net Progress | ||||
2024-11-24 | No Visit | Work Detail | Net Progress | ||||
2024-11-23 | No Visit | Work Detail | Net Progress | ||||
2024-11-22 | No Visit | Work Detail | Net Progress | ||||
2024-11-21 | No Visit | Work Detail | Net Progress | ||||
2024-11-20 | No Visit | Work Detail | Net Progress | ||||
2024-11-19 | No Visit | Work Detail | Net Progress |