Column Filters
Field Visit Report
Name of Work | Providing water supply (Dirba) |
Agency Name | Sh. Tarsem Chand Garg |
Project Cost | Rs 66 Lacs |
Start Date | 06-03-2013 |
End Date | 05-09-2013 |
Expected Date Of Completion | 05-09-2013 |
Je Incharge | Sh. Simranjeet Singh |
SDE Incharge | Sh. Gurpreet Singh Sekhon |
Engineer Incharge | Sh. Amandeep Singh |
Dates | |||||||
---|---|---|---|---|---|---|---|
2024-11-21 | No Visit | Work Detail | Net Progress | ||||
2024-11-20 | No Visit | Work Detail | Net Progress | ||||
2024-11-19 | No Visit | Work Detail | Net Progress | ||||
2024-11-18 | No Visit | Work Detail | Net Progress | ||||
2024-11-17 | No Visit | Work Detail | Net Progress | ||||
2024-11-16 | No Visit | Work Detail | Net Progress | ||||
2024-11-15 | No Visit | Work Detail | Net Progress | ||||
2024-11-14 | No Visit | Work Detail | Net Progress | ||||
2024-11-13 | No Visit | Work Detail | Net Progress | ||||
2024-11-12 | No Visit | Work Detail | Net Progress | ||||
2024-11-11 | No Visit | Work Detail | Net Progress | ||||
2024-11-10 | No Visit | Work Detail | Net Progress | ||||
2024-11-09 | No Visit | Work Detail | Net Progress | ||||
2024-11-08 | No Visit | Work Detail | Net Progress | ||||
2024-11-07 | No Visit | Work Detail | Net Progress |