Scope of Work Component Wise |
|
1.892 |
22.259 |
|
|
|
|
2600 |
1 |
|
|
Progress during this week |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Progress Till Date |
KM |
1.892 KM |
21.25 KM |
% |
% |
|
|
2450 |
100 % |
% |
% |
Financial Progress : | 229 Lacs |
Physical Progress : | 40 % |
Is any observation pending by 3rd Party : | |
Date of Visit by Je: | 2019-07-24 12:11:18 |
Comment by JE in last visit : | Work stopped due to no availability of labor at site |
Observation Raised by JE : | All is well |
Date of Visit by SDO : | 2019-05-29 10:36:55 |
Comment by SDO : | Manhole plaster work in progress |
Observation Raised by SDO : | |
Date of Visit by XEN : | 2019-07-13 14:43:22 |
Comment by XEN on last visit : | Raft work completed |
Observation Raised by XEN : | |
Date of Visit by SE : | |
Comment by SE on last visit : | |
Observation Raised by SE : | |
Date of Visit by CE : | 2018-07-19 13:20:45 |
Comment by CE on last visit : | Link between Dasuya road and sham churasi road , interlocking work is in progress. Bed concrete of interlocking tiles relaying worked checked 1:8:16 checked and found 4 inch thick which is ok |
Observation Raised by CE : | |
Comment by EIC : | KIND ATTENTION
1. Visit during last 30 days of XEN and SE is not on record
2. Kindly upload work component's close view photo to see the quality and workmanship.Avoid self / equipment / machinery etc. or taken from distance photos 3.Examine the bottlenecks and hinderances in execution of work and solve them to complete it within stipulated period
4. otherwise proceed as per CA |
Observation Raised by EIC : | Need urgent intervention from Local Level |
Pending material Inspection Reports : | No |
Any Drawings pending for approval with xen: | No |
Any 3rd Party Inspection Report Pending for compliance : | No |