Scope of Work Component Wise |
|
|
|
|
|
19.67 |
2620 |
|
|
|
|
Progress during this week |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Progress Till Date |
19.6 KM |
KM |
KM |
% |
% |
2620 |
2620 |
|
% |
% |
% |
Financial Progress : | 336 Lacs |
Physical Progress : | 100 % |
Is any observation pending by 3rd Party : | |
Date of Visit by Je: | 2019-03-23 12:36:27 |
Comment by JE in last visit : | Dismantling of CC for laying of 100 mm I'd do k-7 water line |
Observation Raised by JE : | All is well |
Date of Visit by SDO : | 2019-03-27 12:50:19 |
Comment by SDO : | Dismantling of CC road for Laying 100 mm i/d Pipe Line Work in Progress |
Observation Raised by SDO : | |
Date of Visit by XEN : | 2019-03-27 12:50:14 |
Comment by XEN on last visit : | Minimum depth of pipe is not ok....ask sde and he to relay pipe properly. Paki gali tahi mohali area ferozpur and maintain alignment also |
Observation Raised by XEN : | Need Intervention from Local Level |
Date of Visit by SE : | |
Comment by SE on last visit : | |
Observation Raised by SE : | |
Date of Visit by CE : | 2018-05-02 10:19:03 |
Comment by CE on last visit : | Excavation for laying 4id DI PIPES IS IN PROGRESS.
Xen has been instructed to conduct hydro pressure test regularly |
Observation Raised by CE : | |
Comment by EIC : | |
Observation Raised by EIC : | |
Pending material Inspection Reports : | Yes (1)-2018-07-27 11:36:40 |
Any Drawings pending for approval with xen: | No |
Any 3rd Party Inspection Report Pending for compliance : | No |