Progress Report

Column Filters

Weekly Reports

Name of WorkProviding Water Supply work (Under AMRUT)(Ferozepur)
Agency NameSh. Arunesh Gupta Contractor Panchkula
Project CostRs 327 Lacs
Start Date 09-10-2017
End Date08-04-2018
Revised Date08-04-2018
Je InchargeSh. Gurwinder Singh
SDE InchargeSh. Gulshan Kumar
Engineer InchargeSh.Pritpal Singh
Components Program water supply Main sewer Lateral sewer Tubewell Stp Water supply Water supply conn Sewer conn Mps Ohsr Wtp
Scope of Work Component Wise 19.67 2620
Progress during this week 0 0 0 0 0 0 0 0 0 0 0
Progress Till Date 19.6 KM KM KM % % 2620 2620 % % %
Financial Progress :336 Lacs
Physical Progress :100 %
Is any observation pending by 3rd Party :
Date of Visit by Je:2019-03-23 12:36:27
Comment by JE in last visit :Dismantling of CC for laying of 100 mm I'd do k-7 water line
Observation Raised by JE :All is well
Date of Visit by SDO :2019-03-27 12:50:19
Comment by SDO :Dismantling of CC road for Laying 100 mm i/d Pipe Line Work in Progress
Observation Raised by SDO :
Date of Visit by XEN :2019-03-27 12:50:14
Comment by XEN on last visit :Minimum depth of pipe is not ok....ask sde and he to relay pipe properly. Paki gali tahi mohali area ferozpur and maintain alignment also
Observation Raised by XEN :Need Intervention from Local Level
Date of Visit by SE :
Comment by SE on last visit :
Observation Raised by SE :
Date of Visit by CE :2018-05-02 10:19:03
Comment by CE on last visit :Excavation for laying 4id DI PIPES IS IN PROGRESS. Xen has been instructed to conduct hydro pressure test regularly
Observation Raised by CE :
Comment by EIC :
Observation Raised by EIC :
Pending material Inspection Reports :Yes (1)-2018-07-27 11:36:40
Any Drawings pending for approval with xen:No
Any 3rd Party Inspection Report Pending for compliance :No