Scope of Work Component Wise |
|
|
|
|
|
|
|
|
|
3 |
|
Progress during this week |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Progress Till Date |
KM |
KM |
KM |
% |
% |
|
|
|
% |
100 % |
% |
Financial Progress : | 231 Lacs |
Physical Progress : | 100 % |
Is any observation pending by 3rd Party : | |
Date of Visit by Je: | 2018-04-17 10:01:58 |
Comment by JE in last visit : | 99% completed. Testing in progress |
Observation Raised by JE : | All is well |
Date of Visit by SDO : | 2018-04-17 10:04:28 |
Comment by SDO : | Testing of OHSR is in progress |
Observation Raised by SDO : | |
Date of Visit by XEN : | 2018-03-22 15:25:16 |
Comment by XEN on last visit : | Work completed. Except testing |
Observation Raised by XEN : | |
Date of Visit by SE : | 2018-03-22 15:31:14 |
Comment by SE on last visit : | Construction work completed. Testing not yet done.EE advised to test and commission |
Observation Raised by SE : | |
Date of Visit by CE : | |
Comment by CE on last visit : | |
Observation Raised by CE : | |
Comment by EIC : | Site not visited by any officer in last 15 days except once by JE |
Observation Raised by EIC : | Need urgent intervention from Local Level |
Pending material Inspection Reports : | No |
Any Drawings pending for approval with xen: | No |
Any 3rd Party Inspection Report Pending for compliance : | No |