Name of Work | Construction of OHSR, UGSR, Pump chamber, rising main, clear water sump well, distribution lines, pumping machinery etc at Pujjan Wala Mohalla at Bathinda(Bathinda) |
Agency Name | M/s Kulwant Singh Sandhu |
Project Cost | Rs 169 Lacs |
Start Date | 07-02-2019 |
End Date | 06-02-2020 |
Revised Date | 06-02-2020 |
Je Incharge | Sh. Maninder Singh |
SDE Incharge | Sh. Vikramjit Singh |
Engineer Incharge | Sh. Gurvinder Pal Singh |
Components | Program water supply | Main sewer | Lateral sewer | Tubewell | Stp | Water supply | Water supply conn | Sewer conn | Mps | Ohsr | Wtp |
---|---|---|---|---|---|---|---|---|---|---|---|
Scope of Work Component Wise | 2.478 | 2 | |||||||||
Progress during this week | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Progress Till Date | 1150 KM | KM | KM | % | % | % | 100 % | % | |||
Financial Progress : | 0 Lacs | ||||||||||
Physical Progress : | 0 % | ||||||||||
Is any observation pending by 3rd Party : | |||||||||||
Date of Visit by Je: | 2019-07-19 17:24:51 | ||||||||||
Comment by JE in last visit : | Today visited site. Ohsr 3rd brace coloumn work concreting was in progress . Pipe work delayed due to not reaching of pipe at site. But 150 mm pipe reached at site and stack along road | ||||||||||
Observation Raised by JE : | Red Flag | ||||||||||
Date of Visit by SDO : | 2019-07-19 17:32:12 | ||||||||||
Comment by SDO : | Agreed with je comments .ohsr construction work is running as per target but ws laying work is slow pipes laid at | ||||||||||
Observation Raised by SDO : | |||||||||||
Date of Visit by XEN : | 2019-07-19 17:36:02 | ||||||||||
Comment by XEN on last visit : | Material not stagged properly.Agency is advised to take precautionary measure as site is very combusted for OHSR.Sieve apparatus is not at site.Civil work of UGSR completed.Work above third brace is in progress. | ||||||||||
Observation Raised by XEN : | |||||||||||
Date of Visit by SE : | |||||||||||
Comment by SE on last visit : | |||||||||||
Observation Raised by SE : | |||||||||||
Date of Visit by CE : | |||||||||||
Comment by CE on last visit : | |||||||||||
Observation Raised by CE : | |||||||||||
Comment by EIC : | |||||||||||
Observation Raised by EIC : | |||||||||||
Pending material Inspection Reports : | No | ||||||||||
Any Drawings pending for approval with xen: | No | ||||||||||
Any 3rd Party Inspection Report Pending for compliance : | No |