Progress Report

Column Filters

Weekly Reports

Name of WorkProv. W/S & Sew. in extended limit of M.C. Phagwara town Distt. Kapurthala. (Phagwara)
Agency NameM/s Fludyne Systems
Project CostRs 31 Lacs
Start Date 27-02-2019
End Date26-05-2019
Revised Date26-06-2019
Je InchargeSh. Sukhwinder Singh
SDE InchargeSh. Tilak Raj
Engineer InchargeSh. Sunny Gogna
Components Program water supply Main sewer Lateral sewer Tubewell Stp Water supply Water supply conn Sewer conn Mps Ohsr Wtp
Scope of Work Component Wise
Progress during this week 0 0 0 0 0 0 0 0 0 0 0
Progress Till Date KM KM KM % % % % %
Financial Progress :34 Lacs
Physical Progress :100 %
Is any observation pending by 3rd Party :
Date of Visit by Je:2019-06-12 14:31:09
Comment by JE in last visit :Work in progress
Observation Raised by JE :All is well
Date of Visit by SDO :2019-06-12 14:35:44
Comment by SDO :Work in prigress
Observation Raised by SDO :
Date of Visit by XEN :
Comment by XEN on last visit :
Observation Raised by XEN :
Date of Visit by SE :
Comment by SE on last visit :
Observation Raised by SE :
Date of Visit by CE :
Comment by CE on last visit :
Observation Raised by CE :
Comment by EIC :
Observation Raised by EIC :
Pending material Inspection Reports :No
Any Drawings pending for approval with xen:No
Any 3rd Party Inspection Report Pending for compliance :No