Progress Report

Column Filters

Weekly Reports

Name of WorkBoring and installatin of Tubewell(Kharar MC funded)(Kharar)
Agency Nameoberoi tubewell company ludhiana
Project CostRs 108 Lacs
Start Date 29-01-2018
End Date28-07-2018
Revised Date30-09-2018
Je InchargeSh. Rajnish Painuli
SDE InchargeSh. Tarun Gupta
Engineer InchargeSh. Rahul Kaushal
Components Program water supply Main sewer Lateral sewer Tubewell Stp Water supply Water supply conn Sewer conn Mps Ohsr Wtp
Scope of Work Component Wise 4
Progress during this week 0 0 0 0 0 0 0 0 0 0 0
Progress Till Date KM KM KM 100 % % % % %
Financial Progress :101 Lacs
Physical Progress :100 %
Is any observation pending by 3rd Party :
Date of Visit by Je:2018-10-20 10:27:13
Comment by JE in last visit :work completed and electricity connection applied by MC.
Observation Raised by JE :All is well
Date of Visit by SDO :2018-10-04 17:04:55
Comment by SDO :Pump chamber if badala road tubewell in progress
Observation Raised by SDO :
Date of Visit by XEN :2018-10-04 17:19:00
Comment by XEN on last visit :Pump chamber work in progress.
Observation Raised by XEN :
Date of Visit by SE :2018-06-08 10:31:07
Comment by SE on last visit :Development with compressor completed. With submersible, lowering and pump chamber need to be expedited.
Observation Raised by SE :
Date of Visit by CE :2018-07-12 10:26:07
Comment by CE on last visit :Tubewell at Stadium Mundi Kharar commissioned except gravel pit, installation of chlorinator and land scaping. Field staff instructed to complete balance work within 15 days. Tubewell at Chajjumajra also visited, field staff instructed to commission the tubewell after enhancement of electric load. Balance funds may also get deposited from MC before taking further work in hand.
Observation Raised by CE :
Comment by EIC :KIND ATTENTION SE Bathinda 1. Visit of officer above EE during last 30 days is not on record 2. Ensure that the tube well assembly to be lowered should be go approved from the XEn and record of that be maintained
Observation Raised by EIC :Need urgent intervention from Local Level
Pending material Inspection Reports :No
Any Drawings pending for approval with xen:No
Any 3rd Party Inspection Report Pending for compliance :No