Progress Report

Column Filters

Weekly Reports

Name of WorkProv Sewer,STp Barnala Amrut(Barnala)
Agency NameM/s Girdhari Lal Aggarwal
Project CostRs 9293 Lacs
Start Date 16-12-2016
End Date15-06-2018
Revised Date15-06-2018
Je InchargeSh. Tarun Kumar
SDE InchargeSh. Rajinder Kumar Garg
Engineer InchargeSh. Amandeep Singh
Components Program water supply Main sewer Lateral sewer Tubewell Stp Water supply Water supply conn Sewer conn Mps Ohsr Wtp
Scope of Work Component Wise 10.73 63.14 1 No (20) 7200 1
Progress during this week 0 0 0 0 0 0 0 0 0 0 0
Progress Till Date 0 KM 10.12 KM 63.97 KM 0 % 100 % 5740 100 % 0 % 0 %
Financial Progress :9085 Lacs
Physical Progress :100 %
Is any observation pending by 3rd Party :
Date of Visit by Je:2019-07-29 13:05:08
Comment by JE in last visit :Interlocking tile work in progress at bhaini basti at Barnala
Observation Raised by JE :All is well
Date of Visit by SDO :2019-07-22 12:27:43
Comment by SDO :Interested locking work in progress
Observation Raised by SDO :
Date of Visit by XEN :2020-02-04 15:40:08
Comment by XEN on last visit :Work of 1100 mm dia sewer is in progress. Agency is directed to complete balance work earliest
Observation Raised by XEN :
Date of Visit by SE :2018-08-09 16:13:59
Comment by SE on last visit :Mechanical work of STP in progress. STP & MPS likely to be completed by Dec. IL pavers work was in progress on Gali no 8, Baharli have listed, Sangrur. Cross profile/camber of road was not correct as there were local depressions. EE & Agency were asked to dismantle and relay the defective work.Agency asked to start main sewer on Bajakhana to Bus stand Road. Major length of main sewer held up on account of traffic diversion on main internal roads because of non completion of ROB by PWD(B&R). EE asked to personally follow up the case for Forest clearance with DFO (Sangrur).
Observation Raised by SE :
Date of Visit by CE :
Comment by CE on last visit :
Observation Raised by CE :
Comment by EIC :Kind attn SE Pta Kindly get the permissions from other departments with out further delays
Observation Raised by EIC :Need urgent intervention from Local Level
Pending material Inspection Reports :No
Any Drawings pending for approval with xen:No
Any 3rd Party Inspection Report Pending for compliance :Yes