Progress Report

Column Filters

Weekly Reports

Name of WorkProvidng 100% W/S old limit phagwara(Phagwara)
Agency NameM/S Dhruv Tubewell Engineers
Project CostRs 136 Lacs
Start Date 27-09-2016
End Date26-03-2017
Revised Date26-03-2017
Je InchargeSh. Sukhwinder Singh
SDE InchargeSh. Tilak Raj
Engineer InchargeSh. Sunny Gogna
Components Program water supply Main sewer Lateral sewer Tubewell Stp Water supply Water supply conn Sewer conn Mps Ohsr Wtp
Scope of Work Component Wise 10
Progress during this week 0 0 0 0 0 0 0 0 0 0 0
Progress Till Date 0 KM 0 KM 0 KM 9 % 0 % 0 0 % 0 % 0 %
Financial Progress :713 Lacs
Physical Progress :90 %
Is any observation pending by 3rd Party :
Date of Visit by Je:2018-05-04 12:00:45
Comment by JE in last visit :9 nos. Tubewell completed out of 10 no. Tubewell. MAC has not handed over the remaining site of tubewell. Work completed
Observation Raised by JE :Red Flag
Date of Visit by SDO :2018-05-04 12:06:20
Comment by SDO :Work completed Final bill under process
Observation Raised by SDO :
Date of Visit by XEN :2018-05-04 12:13:43
Comment by XEN on last visit :Work of 9 No. Tubewells completed by firm. One site of tubewell not handed over by M.C. at onkar nagar. The work stands completed. Sde and JE is directed to finalise the accounts of this agreement in one week.
Observation Raised by XEN :
Date of Visit by SE :2018-03-23 18:41:11
Comment by SE on last visit :All the 9 nos are.commissioned. xen to take up the matter with MC phagwara for the site of 1 No. Pending tubewell so.that work can be finalised
Observation Raised by SE :
Date of Visit by CE :
Comment by CE on last visit :
Observation Raised by CE :
Comment by EIC :
Observation Raised by EIC :
Pending material Inspection Reports :No
Any Drawings pending for approval with xen:No
Any 3rd Party Inspection Report Pending for compliance :No