Scope of Work Component Wise |
|
|
|
10 |
|
|
|
|
|
|
|
Progress during this week |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Progress Till Date |
0 KM |
0 KM |
0 KM |
9 % |
0 % |
|
|
0 |
0 % |
0 % |
0 % |
Financial Progress : | 713 Lacs |
Physical Progress : | 90 % |
Is any observation pending by 3rd Party : | |
Date of Visit by Je: | 2018-05-04 12:00:45 |
Comment by JE in last visit : | 9 nos. Tubewell completed out of 10 no. Tubewell. MAC has not handed over the remaining site of tubewell. Work completed |
Observation Raised by JE : | Red Flag |
Date of Visit by SDO : | 2018-05-04 12:06:20 |
Comment by SDO : | Work completed
Final bill under process |
Observation Raised by SDO : | |
Date of Visit by XEN : | 2018-05-04 12:13:43 |
Comment by XEN on last visit : | Work of 9 No. Tubewells completed by firm. One site of tubewell not handed over by M.C. at onkar nagar. The work stands completed. Sde and JE is directed to finalise the accounts of this agreement in one week. |
Observation Raised by XEN : | |
Date of Visit by SE : | 2018-03-23 18:41:11 |
Comment by SE on last visit : | All the 9 nos are.commissioned. xen to take up the matter with MC phagwara for the site of 1 No. Pending tubewell so.that work can be finalised |
Observation Raised by SE : | |
Date of Visit by CE : | |
Comment by CE on last visit : | |
Observation Raised by CE : | |
Comment by EIC : | |
Observation Raised by EIC : | |
Pending material Inspection Reports : | No |
Any Drawings pending for approval with xen: | No |
Any 3rd Party Inspection Report Pending for compliance : | No |