Progress Report

Column Filters

Weekly Reports

Name of Workproviding laying sewerage work (Sub Contract No. JICA-004-05)(Amritsar(MC))
Agency NameM/s. Oriental Ceramics Refractories
Project CostRs 1139 Lacs
Start Date 21-07-2017
End Date22-01-2018
Revised Date22-01-2018
Je InchargeSh. Aman Kumar (vacant)
SDE InchargeSh. Gurdeep Arora
Engineer InchargeSh. S.K.Ranga
Components Program water supply Main sewer Lateral sewer Tubewell Stp Water supply Water supply conn Sewer conn Mps Ohsr Wtp
Scope of Work Component Wise 22.84
Progress during this week 0 0 0 0 0 0 0 0 0 0 0
Progress Till Date KM KM 12.39 KM % % 2600 % % %
Financial Progress :1135 Lacs
Physical Progress :100 %
Is any observation pending by 3rd Party :
Date of Visit by Je:2018-08-27 15:46:39
Comment by JE in last visit :Construction of 1000mm I'd manhole near verka chownk
Observation Raised by JE :All is well
Date of Visit by SDO :
Comment by SDO :
Observation Raised by SDO :
Date of Visit by XEN :2018-08-03 13:46:45
Comment by XEN on last visit :Excavation of 1000 mm diameter sewer at Batala road. Approx 60 mtr gap was left by Jyoti buildtech. Out of which 30 mtr has been laid. Work stopped today by factory owner has now been resumed with intervention of area councilor. Pipe laying likely to be completed tomorrow.
Observation Raised by XEN :
Date of Visit by SE :2018-09-12 10:45:21
Comment by SE on last visit :MH at 1000 mm constructed. Laying of slab is pending which will be laid tomorrow.
Observation Raised by SE :
Date of Visit by CE :
Comment by CE on last visit :
Observation Raised by CE :
Comment by EIC :It may ensured that work be done accordingly PWSSB specification strictly.
Observation Raised by EIC :Need Intervention from Local Level
Pending material Inspection Reports :No
Any Drawings pending for approval with xen:No
Any 3rd Party Inspection Report Pending for compliance :No