Progress Report

Column Filters

Weekly Reports

Name of Workproviding laying sewerage work (Sub Contract No. JICA-004-05)(Amritsar(MC))
Agency NameM/s. Oriental Ceramics Refractories
Project CostRs 1139 Lacs
Start Date 21-07-2017
End Date22-01-2018
Revised Date31-05-2018
Je InchargeSh. Rajeev Kumar
SDE InchargeSh. Gurdeep Arora
Engineer InchargeSh. S.K.Ranga
Components Program water supply Main sewer Lateral sewer Tubewell Stp Water supply Water supply conn Sewer conn Mps Ohsr Wtp
Scope of Work Component Wise 1.97
Progress during this week 0 0 0 0 0 0 0 0 0 0 0
Progress Till Date KM 2025 KM KM % % % % %
Financial Progress :1135 Lacs
Physical Progress :100 %
Is any observation pending by 3rd Party :
Date of Visit by Je:2018-08-01 16:47:45
Comment by JE in last visit :Plaster work for manhole at Majitha Road 1800mm RCC pipe line
Observation Raised by JE :All is well
Date of Visit by SDO :2018-05-28 17:54:18
Comment by SDO :Manhole no. 7 majitha road
Observation Raised by SDO :
Date of Visit by XEN :2018-07-14 17:34:02
Comment by XEN on last visit :Excavation of 1800 mm- 2000mm junction manhole at majitha road in progress. This manhole is needed to be constructed at earliest as it is causing inconvenience in traffic movement. Further due to rain, it becomes very difficult to work as vehicles often get stuck causing traffic jam. Agency is directed to complete this work immediately also provide barricading around the excavation.
Observation Raised by XEN :
Date of Visit by SE :2018-08-08 09:51:49
Comment by SE on last visit :At Majitha Chowk by pass flyover with SE QC and his team for inspection of damage to flyover
Observation Raised by SE :
Date of Visit by CE :2018-04-11 09:53:37
Comment by CE on last visit :Trenchless crossing at Batala road. 75 mtr. done 35 mtr balance. Shuttering arrangement shall be done properly to avoid any mishap.
Observation Raised by CE :
Comment by EIC :1No visit by CE and SDE is on record 2The masonary of the Man Hole seems aged well but still the slab is not laid over it? 3 The work is delayed a lot
Observation Raised by EIC :Need urgent intervention from Local Level
Pending material Inspection Reports :No
Any Drawings pending for approval with xen:No
Any 3rd Party Inspection Report Pending for compliance :No