Scope of Work Component Wise |
|
|
9.24 |
|
|
|
|
1000 |
|
|
|
Progress during this week |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Progress Till Date |
KM |
KM |
9.2 KM |
% |
% |
|
|
776 |
% |
% |
% |
Financial Progress : | 330 Lacs |
Physical Progress : | 100 % |
Is any observation pending by 3rd Party : | |
Date of Visit by Je: | 2018-11-10 12:48:09 |
Comment by JE in last visit : | Premix in progress |
Observation Raised by JE : | All is well |
Date of Visit by SDO : | 2018-10-23 13:13:01 |
Comment by SDO : | PC work in progress |
Observation Raised by SDO : | |
Date of Visit by XEN : | 2019-08-10 14:22:07 |
Comment by XEN on last visit : | Work completed. Visited STP site and working satisfactory |
Observation Raised by XEN : | |
Date of Visit by SE : | 2018-03-19 13:45:15 |
Comment by SE on last visit : | Work is standstill since long. Metalled Road work not started till date. Public is facing lot of hardship. EE Skeffington to explain the action taken by him |
Observation Raised by SE : | Need urgent intervention from Local Level |
Date of Visit by CE : | |
Comment by CE on last visit : | |
Observation Raised by CE : | |
Comment by EIC : | KIND ATTENTION
1. Visit of officer above XEN during last 15 days is not on record
2. Kindly upload work component's close view photo to see the quality and workmanship.Avoid self / equipment / machinery etc. or taken from distance photos
3. Dismantled material should be taken care of side by side and accounted for in books properly
4. Kindly report to my comments dated 4th Apr |
Observation Raised by EIC : | Need urgent intervention from Local Level |
Pending material Inspection Reports : | No |
Any Drawings pending for approval with xen: | No |
Any 3rd Party Inspection Report Pending for compliance : | No |