Progress Report

Column Filters

Weekly Reports

Name of WorkProviding water supply & sewerage work(Ropar)
Agency NameSh. Kuldip Singh Contractor, Chandigarh
Project CostRs 788 Lacs
Start Date 04-01-2016
End Date30-11-2017
Revised Date30-11-2017
Je InchargeSh. Tarun Gupta
SDE InchargeSh. Arvind Mehta
Engineer InchargeSh. Rahul Kaushal
Components Program water supply Main sewer Lateral sewer Tubewell Stp Water supply Water supply conn Sewer conn Mps Ohsr Wtp
Scope of Work Component Wise 9.28 12.26 2627 2367
Progress during this week 0 0 0 0 0 0 0 0 0 0 0
Progress Till Date 14.62 KM KM 12.67 KM % % 1462 1462 823 % % %
Financial Progress :775 Lacs
Physical Progress :100 %
Is any observation pending by 3rd Party :
Date of Visit by Je:2018-05-17 10:36:21
Comment by JE in last visit :Wtp ropar
Observation Raised by JE :All is well
Date of Visit by SDO :2018-04-12 11:55:39
Comment by SDO :No comments
Observation Raised by SDO :
Date of Visit by XEN :2018-04-17 14:20:45
Comment by XEN on last visit :Work completed. STP Rasulpur under stabilization.
Observation Raised by XEN :
Date of Visit by SE :2018-03-21 14:17:18
Comment by SE on last visit :EE to check and ascertain reasons for & take n/a reg variation in quantities of distribution lines, sew lines, metalled/cc/interlocking roads before finalisation of bills
Observation Raised by SE :
Date of Visit by CE :
Comment by CE on last visit :
Observation Raised by CE :
Comment by EIC :If work is completed then contact XEN Mohit Verma for removing it from data
Observation Raised by EIC :Need Intervention from Local Level
Pending material Inspection Reports :No
Any Drawings pending for approval with xen:No
Any 3rd Party Inspection Report Pending for compliance :No