Progress Report

Column Filters

Weekly Reports

Name of WorkProviding Sewerage works in six villages (Nangal)
Agency NameSh. Parveet Singh Contractor, Mohali
Project CostRs 380 Lacs
Start Date 28-04-2015
End Date31-03-2018
Revised Date10-12-2018
Je InchargeSh. Lovekesh Kumar
SDE InchargeSh. Tarun Gupta
Engineer InchargeSh. Rahul Kaushal
Components Program water supply Main sewer Lateral sewer Tubewell Stp Water supply Water supply conn Sewer conn Mps Ohsr Wtp
Scope of Work Component Wise 19.94
Progress during this week 0 0 0 0 0 0 0 0 0 0 0
Progress Till Date KM KM 18.90 KM % % % % %
Financial Progress :372 Lacs
Physical Progress :100 %
Is any observation pending by 3rd Party :
Date of Visit by Je:2018-12-11 13:13:32
Comment by JE in last visit :Work in progress
Observation Raised by JE :All is well
Date of Visit by SDO :2018-11-16 10:21:40
Comment by SDO :
Observation Raised by SDO :
Date of Visit by XEN :2018-10-12 13:39:08
Comment by XEN on last visit :Work progress slow due to shops present on both sides, railway boundary in alignment. Agency instructed to expedite progress by taking proper safety measures. Case for laying sewer in railway boundary to be done by thrusting.
Observation Raised by XEN :
Date of Visit by SE :2018-03-21 11:08:10
Comment by SE on last visit :Progress of Work very slow as time limit is already over
Observation Raised by SE :Need urgent intervention from Local Level
Date of Visit by CE :
Comment by CE on last visit :
Observation Raised by CE :
Comment by EIC :No visit above SDE is on record. work is going on since 4/15 and till date progress is 92%. The photos uploaded are of no technical use.The back filling of earth seems without compacting and watering
Observation Raised by EIC :Need urgent intervention from Local Level
Pending material Inspection Reports :No
Any Drawings pending for approval with xen:No
Any 3rd Party Inspection Report Pending for compliance :No